ExamBro
ExamBro
JEE Mains · Maths · STD 11 - 4.2 Quadratic equations and inequations

A building construction work can be completed by two masons A and B together in 22.5 days. Mason A alone can complete the work in 24 days less than mason B alone. Then mason A alone will complete the work in:

  1. A 24 days
  2. B 42 days
  3. C 30 days
  4. D 36 days
Verified Solution

Answer & Solution

Correct Answer

(D) 36 days

Step-by-step Solution

Detailed explanation

Let time taken by mason a alone to complete the work be in x days so, mason B along take \(x+24\) days work done by A in 1 day \(=\frac{1}{x}\) work done by \(B\) in 1 day \(=\frac{1}{x+24}\) so work done by \(A + B\) in 1 day \(=\frac{1}{22.5}\) So,…
Same subject
Explore more questions on app
From JEE Mains
Explore more questions on app